Details, Details

July 31, 2025

It may look the same on the outside, like nothing is happening, but don’t let that fool you.

Progress on our beautiful new Greenfield Chapel construction continues to move forward toward completion. Now that the building is up, the roof on, the utilities installed, builders’ attention is currently focused on all the beautiful details.

Painting and Finishing, Inside and Out

Over the past few weeks, workers finished hanging drywall and prepping interior rooms for painting. In fact, interior painting should be completed sometime this week.

Doors and trim have already been installed. Over the next couple months workers will install lighting, cabinets, door hardware, flooring etc. The HVAC system should be completed in August.

In other words, the interior of the chapel is coming together nicely. Quite nicely.

Outdoor Challenges

Meanwhile, with recent severe storms dumping inches of rain on an almost daily basis, work on the exterior comes with its own set of challenges.

The weather continues to delay pouring concrete for the pathways, terraces and required parking spaces for people with disabilities.

The underground stormwater management system is substantially complete and site grading is ongoing.

Next Steps? Oh yes! The Altar

The altar is currently scheduled to be installed sometime around the end of August or early September.

As of now, the chapel is still on schedule for completion sometime this fall. The final date is yet to be determined and very much depends on the weather.

Please continue to pray for the safe and successful completion of this project, which, after all, is just one beautiful next step in ongoing plans for Greenfield’s service to Master’s ever-growing world-wide family. And, if  you are able, please do consider making a financial contribution to Greenfield’s building fund.