Construction Update – Footings are poured

October 29, 2024

Really Digging It

They’re at it again. Once again—after a pause that lasted almost three weeks—construction workers returned to Greenfield. Again, the air was rent with the sounds of heavy machinery leveling the ground, digging holes for the new chapel’s footings and foundation.

And (finally!) the actual substance of our new Greenfield Chapel was quite literally poured into all those carefully prepared holes. Click on this link to a time lapse video of all the action last week on the building site.

Why the pause? On October 4, the first day of actual construction, builders discovered a problem involving the alignment of drainage pipes and the chapel’s foundation. Adjusting the depth of the foundation required an engineer’s input and paperwork that needed Greenfield’s attention.

Footings dug and ready for concrete.

That’s all been taken care of. Let’s face it, if you’re going to find a problem, it’s a good thing to have it happen on day one and not further along in the construction process. (Fortunately, the required changes were not of the kind requiring county approval.)